TOGG Gemlik Factory is broadcast live 24/7!

Today, in the details of our news, we will share information about the construction of TOGG Gemlik Factory, which is broadcast live 24/7. TOGG has put the TOGG TV channel on the air for live broadcast. This new project was established to broadcast this information live about the construction of the factory and the construction situation. Now, without further ado, we wanted to move on to the details of the news. Here are the details!

TOGG Gemlik Factory is broadcast live 24/7!

Now, before we tell you about this issue, we wanted to write the reason why. First of all, while there is a lot of support for its construction, there is also a crew that does not believe in it. We really see a lot of people who think this way. Because some people ask these questions like where is the car, where is the factory, not critically, but at the expense of contempt.

Of course, it is not possible for TOGG executives to be unaware of these developments. For this reason, for those who do not believe in photos and news, live broadcasts have been started on TOGG Youtube channel with the #excited tag. Anyone who wants to watch this broadcast can enter and watch.

So where is the factory? Is the car being made? Was the national car business a dream? Are they fooling everyone? It was done to eliminate similar questions. This live broadcast idea also prevented those who spread such false information. In order to present to you that we are very happy with this development, TOGG Gemlik Factory is broadcast live 24/7! We happily wrote the news.

We have presented the live broadcast of TOGG Gemlik Factory below, so that there are no more such days full of lies. Those who are immediately curious can examine the condition of the factory construction. Just below, there will be a TOGG TV link for TOGG live broadcast.

!!!!LIVE BROADCAST END!!!

The completed and ongoing stages at TOGG Gemlik Factory are listed below.

Paint Building: Under-foundation waterproofing works, 85% of foundation iron works, 70% of foundation concrete works have been completed. Column productions started.

Body Production Building: 85% of the sub-foundation waterproofing works, 50% of the foundation iron works, 30% of the foundation concrete works have been completed, Socket production has started.

Assembly Building: 70% of the sub-foundation waterproofing works, 35% of the foundation iron works, 16% of the foundation concrete works have been completed.

Energy Building: Under-foundation waterproofing works, Basic iron works, Foundation concrete works are 100% completed. Column productions started.

The factory completed and started status is as above. Here you can see what has happened and the progress that has been made in the live video.